logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 광주지방법원순천지원 2016.10.13 2014가합12486
공사대금
Text

1. All claims filed by the Plaintiff (Counterclaim Defendant) and the counterclaim claims filed by the Defendant (Counterclaim Plaintiff) are dismissed.

2...

Reasons

1. Basic facts

A. A. A around February 15, 2012, around February 15, 2012, the Defendant’s actual contract entered into G, the husband of the Defendant.

B. In the instant contract, “the instant building”, “the instant construction,” and “the instant contract for the construction of the instant construction,” the content of which is to construct the 6th floor building on D and E’s ground (hereinafter referred to as “instant building,” and “the instant contract for the construction,” under which the contractor was changed to the Plaintiff via F Co., Ltd., but there was no change in the content of the instant contract, and thus, the contract was concluded between the Plaintiff and the Defendant, regardless of whether the contractor was the party. As seen below, the main content is as follows.

Standard contract documents for construction works

4. Period: Amount of contract from February 20, 201 to August 30, 2012: 1,340,240,000 won: 1,218,40,000 won; value-added tax; 121,840,000 won;

9. The rate of warranty bond: 3%; 11. The rate of liquidated damages: The terms and conditions of the construction contract under the special agreement on the construction contract in the amount equivalent to 1/1,000 of the daily contract amount per delay

1. Litch, gas sirens, added to an estimate and calculated separately for household appliances and appliances;

(A)A separate map: air conditioners, TV, laundry, laundry, laundry, bookboards

2. The personal phone in the construction of electric communications shall be calculated separately as the designation of the owner.

(system, including lines, lines, only machinery and apparatus separate)

3. Landscape works shall be constructed at an amount specified in an estimate and adjusted through consultation, unless completion thereof is hindered.

4.The above processes shall be the contents discussed and may be consulted when replacing the depreciations specified in the subsequent details.

5. Survey costs, design costs, and supervision costs are excluded, and all kinds of personal participation costs are borne by a project owner other than the project owner.

Terms and Conditions of Construction Costs Payment

1. 100 million won in cash out of the construction expenses shall be borne by the contractor as the top priority and the substitute shall be 300 million won in case of goods after completion; and

1. Total amount of the construction cost;

arrow