Defendant shall be punished by a fine of KRW 2,000,000.
If the defendant does not pay the above fine, 50,000 won.
Reasons
Punishment of the crime
The Defendant served as the site manager of E Co., Ltd. (hereinafter referred to as “E”) who was subcontracted with the Construction Work for Basic Dredging and Kson C&T from Samsung C&T Co., Ltd. (hereinafter referred to as “E”), on June 3, 2011, the Defendant was a person in charge of safety management for the equipment and number of employees in the construction site including the victim F Co., Ltd. (hereinafter “G”). On June 20, 201, the Defendant attempted to put the instant vessel into the construction site located in Seopo-si, Seopo-si, Seopo-si, P&D on June 20, 201, but delayed due to the construction opposition, the construction delayed on June 22, 2011, caused the instant vessel to temporarily access the instant vessel at the middle point of the breakwater in the same port of Taepo-si, Seopo-si, Seopo-si, Seopo-si, to manage the said vessel in the future.
On the other hand, the typhoon No. 9 of 201, "MUIFA" came into existence on July 28, 201, and developed into a large typhoon of a size of 930 hPa, maximum wind speed of 50 m30 ms, and strong wind radius of 580 ms. On August 1, 201, the vessel of this case began to move into the south coast of Korea with the maximum wind of 945hPa, maximum wind of 45 ms/s, and strong wind of 50 ms, and the Defendant, on August 3, 201, 201, 200: (a) the vessel of this case, which was under the influence of the breakwater at the time of the latest construction division, was inspected in the order of the vessel of this case, and (b) the vessel of this case, which was under the influence of the breakwater at the time of the port of this case, was under the influence of the breakwater at the port of this case.