(영문) 청주지방법원 2015.04.02 2013가합25320 (1)
손해배상청구
Text

1. The plaintiff's claims against the defendants are all dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Basic facts

A. The parties concerned 1) The Plaintiff is a non-profit corporation established under the Credit Unions Act for the purpose of receiving the deposits of its members and lending the loans to its members. (2) Defendant B worked for the Plaintiff Union from October 1993 to December 2012, 200, and was in charge of taking overall charge of lending and receiving the loans from its members since 2004. Defendant C worked for the Plaintiff Union from April 1993 to October 2009, while working for the Plaintiff Union from 2007 to 2007.

3) Meanwhile, D Co., Ltd. E (hereinafter “E”)

2) The Plaintiff’s primary loan execution is a person who, as the representative director, has implemented the new construction and sale business of the building G main complex in G with the size of 38 apartment bonds and 42 commercial buildings from the Chungcheong-gun, Chungcheongnam-gu. The Plaintiff’s primary loan execution of the Plaintiff’s primary loan execution is a loan of KRW 500 million in total to H and I as security each of the “security price” listed below [Attachment] on October 20, 208 (hereinafter “instant primary loan”).

However, on October 25, 2010 and October 25, 2012, the above secured goods were disposed of by public auction, and the total amount of the public auction price was collected as taxes in arrears for the construction and sale company of the above G major complex building, and the Plaintiff failed to recover the total amount of KRW 500 million. Serials offered as security 86,576,000,000, 000 H 201, 202, 2002, 007, 000, 000, 000, 2000, 000, 200, 300, 3103, 201, 200, 200, 200, 200, 3103, 201, 201, 3008, 2005, 301, 2007, 3001, 3007, 20104

C. On September 7, 2010, the Plaintiff’s secondary loan implementation Plaintiff KRW 200 million with the said G 1002 Dong 110 as security, KRW 107 Dong 108 as security, KRW 330 million with the security of KRW 1007 and 108, KRW 100 million with L, KRW 296 million with the security of heading 203 through 206 of 101 Dong 203 and KRW 1040 million with the security of KRW 103 and 1040 million with M.