(영문) 서울동부지방법원 2015.02.04 2014가합11534
물품대금
Text

1. Defendant A Co., Ltd. shall pay to the Plaintiff KRW 203,270,00 and the interest thereon from December 28, 2014 to the date of full payment.

Reasons

1. According to the overall purport of evidence Nos. 1 and 2 as to Defendant A, the Plaintiff supplied work to Defendant A during the period from April 24, 2014 to May 29, 2014, and the total price of the goods was 244,467,000, and the Plaintiff received reimbursement of KRW 41,197,00 from the above Defendant.

Thus, the above defendant is obligated to pay to the plaintiff 203,270,000 won for remaining goods and damages for delay calculated at the rate of 20% per annum from December 28, 2014 to the date of full payment, which is clear that it is the day following the delivery of a copy of the complaint of this case.

2. The plaintiff filed a claim against the defendant B against the defendant B for joint and several payment of the above goods, but there is no evidence to acknowledge the joint and several liability of the defendant B.

3. In conclusion, the plaintiff's claim against the defendant A is accepted on the ground of its reasoning, and the claim against the defendant B is dismissed as it is without merit. It is so decided as per Disposition.