(영문) 창원지방법원마산지원 2015.11.20 2014가합727
공사대금
Text

1. The Defendants jointly share the Plaintiff A Co., Ltd. with KRW 129,114,00, and KRW 40,500,000, and Plaintiff B Co., Ltd.

Reasons

1. Basic facts

A. On July 18, 2012, Plaintiff A Co., Ltd. (hereinafter “Plaintiff A”) and Defendant D D Co., Ltd. (hereinafter “Defendant Co., Ltd”) entered into a construction contract with Defendant Company and Kimhae-si, setting the construction cost of KRW 4,730,00 for water supply and drainage works among the newly constructed construction works of the F building in the Kimhae-si, Kimhae-si. On November 15, 2012, Plaintiff A entered into a construction contract with Defendant Company and the construction cost of KRW 19,690,00 for water supply and drainage works among the newly constructed construction works of the two lots of land outside Chang-si, Changwon-si, Changwon-si, and KRW 25,00,00 for water supply and drainage works, and each construction contract was concluded with the respective construction cost of KRW 25,50,000 for water supply and drainage works among the newly constructed construction works of H two complex construction works.

3) On December 23, 2012, Plaintiff A entered into a construction contract with Defendant Company and H 1 Complex Construction Costs of KRW 47,800,000 for water supply and drainage installation works among H 2 Complex Construction Works, and KRW 50,000 for water supply and drainage installation works among H 2 Complex Construction Works. On December 25, 2012, Plaintiff A entered into a construction contract with Defendant Company at KRW 50,000 for water supply and drainage installation works among the above H 3 Complex Construction Works. On January 3, 2013, Plaintiff A and Defendant Company entered into a construction contract with Plaintiff Company at KRW 76,714,00 for additional installation works as above, but did not receive KRW 129,14,00 for construction works from Defendant Company.

B. On December 20, 2012, Plaintiff B Co., Ltd. (hereinafter “Plaintiff B”) and Defendant Co., Ltd. (hereinafter “Defendant Co., Ltd”) concluded each contract for construction with the respective cost of KRW 16,83,00 for packaging construction among the new construction works of H 1 Complex Construction, and KRW 16,83,00 for H 2 Complex Construction, and KRW 16,83,00 for packing construction among the new construction works of H 3 Complex Construction. (2) The Plaintiff B concluded each contract for construction.