Text
1. All of the plaintiff's claims are dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
Reasons
1. Name of the course of the disposition: 36 months from the date of commencement - The first year: the creation of a facility and the commencement of a test style - the budget for the two to three years: the budget for the test style and the management required: 2 billion won (50 billion won at the expense of 50%): The major contents: the creation of a festival breeding farm (1 billion won at the expense of 1 billion won) and the test style and management of marine ginseng (1 billion won at the expense of 1 billion won): the method of implementation at a place where consultation is possible first among the candidates as a result of a lot of investigation in 2013: the results of the creation of a festival and test style: Model of aquaculture: the Government-invested research institute, university or research institute established under Article 32 of the Civil Act, the non-profit specialized research institute established under the Government-invested research institute, the university or the Civil Act, and the test style.
A. On June 20, 2014, the Defendant publicly announced the “B Project Promotion Plan” (hereinafter “instant project”).
The main contents of the instant project are as follows.
B. On July 10, 2014, the Plaintiff filed a business application with the Defendant, and submitted a business plan with D fishery partnership corporations (hereinafter “foreign corporation”) and E fishery partnership corporations as participants (hereinafter “instant business plan”).
C. On September 24, 2014, the Defendant selected the Plaintiff as a business entity through the announcement of the business plan, on-site inspection, etc. by the business applicants, including the Plaintiff, and notified the Plaintiff thereof.
After that, on July 7, 2015, the Defendant changed the business place from “F” located in Ansan-si to “G” located in Chungcheongnam-do, and the business period from “from October 2014 to September 2017” to “from July 7, 2015 to June 2018.”
On July 27, 2015, the Plaintiff filed a claim with the Defendant for the payment of KRW 800 million national subsidies, and the Defendant, on July 28, 2015, rendered a decision to grant the national subsidies (hereinafter referred to as “decision to grant the first national subsidies”) to the Plaintiff, who is a subsidized project operator, to pay KRW 80 million to the Plaintiff, and the national subsidies are KRW 80 million to the Plaintiff.