(영문) 광주지방법원목포지원 2017.12.06 2017가단528
토지인도 등
Text

1. Defendant B Co., Ltd.:

A. Of the 303,035 square meters in Jeon-gun, Chungcheongnam-gun, Chungcheongnam-gun, the indication of 7, 8, 9, 10, 11 of the attached Form 1 shall be as follows.

Reasons

. This case’s business contract is called the business contract of this case

Article 2 (Terms and Conditions of Contracts) (1) The project is the second parking lot of the Hap-gun H Building 2 (hereinafter referred to as the “parking lot”) of the Hap-gun, Hap-gun, Hap-gun, as follows.

(1) The site(hereinafter referred to as “the site”) shall be referred to as “the site,” and the details shall be as follows:

(3) Eul (hereinafter referred to as a "business entity") is a special purpose corporation (SPC) called "I" (hereinafter referred to as a "business entity") for the project period in order to construct the relevant parking lot and make it available for G development in the upper part.

Article 3 (Business Period) (1) The instant business period is as follows: The date when 15 years have elapsed from the date of the commencement of commercial operation (the date of commencement of commercial operation begins with the approval of the competent authorities in fact in accordance with the procedures required under the laws and regulations and at the time when normal charges are imposed), Article 4 (1) A shall hold a J (the completion of subordinate civil works on the parking lot site shall be completed by no later than 2 months before K2 months, and the Basic Civil Works Corporation for the Construction of Power Plants at the time of the subordinate civil works shall cooperate to ensure that the Basic Civil Works Corporation for the Construction of Power Plants at the time of the subordinate civil works shall be concurrently carried out by the J 3 months prior to the opening of the J.

(2) A shall lease the upper portion of the site of this parking lot to B during the period of the instant project and take all measures necessary to establish and operate the instant power plant using the site of this parking lot during the instant project period for B.

(3) A shall build, maintain, and manage electric power plants, including authorization and permission, for the construction of electric power plants in Eul.