logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 수원지방법원성남지원 2014.11.05 2013가단35534
사용료
Text

1. The Defendants jointly and severally agreed to KRW 35,568,825 against the Plaintiff and 6% from May 1, 2013 to November 5, 2014.

Reasons

1. In addition to the purport of the entire pleadings in the statement in Gap evidence No. 1, the plaintiff, as a lessor of building materials, concluded a contract on October 18, 201 that "the confirmation of building materials shall be confirmed by the certificate of acceptance and transaction statement of the above defendant", and the rent shall be paid in accordance with the monthly contract between the plaintiff and the subordinate construction (the last day of each month and the cash payment on the 15th following month) based on the agreement between the plaintiff and the defendant (the last day of each month, the number of days of use x the basic fee x the number of days)" (hereinafter referred to as "the lease contract in this case"), the defendant A limited liability company (hereinafter referred to as "the defendant") and the defendant Eeeeeeeeeeeeeeeeeeeeeeeeee Co., Ltd. (hereinafter referred to as "the defendant Eeeeeeeeeeeeng") for the lease contract."

2. The parties' assertion

A. According to the instant lease agreement, the Plaintiff leased the snow construction material to Defendant subordinate Construction from October 20, 201 to April 30, 2013 under the instant lease agreement, but did not receive rent of KRW 35,98,000, so the Defendants are jointly and severally liable to pay it.

Even if the above defendant is not admitted to be liable to the above defendant as alleged subsequent to the construction of sub-construction, the above defendant cannot be exempted from the liability of the nominal lender under Article 24 of the Commercial Act.

B. On November 14, 201, the construction contract was terminated upon the conclusion of the construction agreement on the construction of a joint facility for livestock excreta resource-generating in 2010, which was entered into with the Defendant Erae Environment, and the said construction contract was later concluded on November 15, 201 on November 15, 201. The Defendant Erae Environment entered into a subcontract for the construction company as a limited company and the said construction project.

arrow