(영문) 부산지방법원 2015.08.20 2012가합22276
매매대금등
Text

1. The Defendant’s KRW 441,961,567 among the Plaintiff and KRW 406,108,893 among the Plaintiff, shall be KRW 35,852,67.

Reasons

1. Basic facts

A. On November 26, 2011, the original and the Defendant entered into a contract with the following terms (hereinafter “instant contract”) and entered into a sales contract (hereinafter “instant contract”) based on the content of A’s evidence Nos. 1 through 3, as seen in paragraph (2) below.

A seller: The plaintiff, the defendant, and both the buyer and the buyer enter into a sales contract with respect to the following real estate:

1. Indication of real estate - Location: Geum-gu Busan Metropolitan City - Land: 211 square meters (hereinafter “instant land”) - Building: Multi-household housing in reinforced concrete structure (hereinafter “instant building”);

2. Terms and conditions of contract - Amount of 1,060,000 - Contract amount of 30,000,000 won: 30,000 won shall be paid and received at the time of the contract. - Heavy amount of 440,000,000 won shall be paid on December 23, 201.

30,000,000 won shall be paid on December 27, 2011.

- Balance: 560,000,000 won shall be paid on May 31, 2012

Article 2 (Transfer, etc. of Ownership) A seller shall, at the same time as the receipt of the balance of the purchase price, deliver all documents necessary for the registration of transfer of ownership to a purchaser and cooperate with the registration procedures, and the delivery date of the said real estate shall be May 31, 20

On December 23, 2011, the ownership of land shall be transferred at the time of intermediate payment and the change of the name of the owner shall also be concurrently conducted.

-the structure and overall construction of the building shall be constructed on the basis of the permit drawings of the building, and the additional amounts due to the modification of the design at the buyer's request shall be borne separately by

-The seller shall be responsible for, complete, and complete all matters concerning the construction until completion, and the seller shall order the buyer to use if the buyer pays the balance.

Provided, That the seller shall be subtracted from the balance when the building is completed.

B. The Plaintiff’s total sum of KRW 30,000,000, intermediate payment of KRW 470,000,000, and partial remainder of KRW 100,000,000, not later than the date of closing the argument.