logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 인천지방법원 2014.09.24 2014가합2019
채무부존재확인 등
Text

1. All of the plaintiff's claims are dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

Basic Facts

On March 9, 2001, the head of the Incheon Metropolitan City Urban Development Headquarters established a land substitution plan for a land readjustment project implemented in the area of 944,776 square meters of Seo-gu, Incheon Metropolitan City, Seo-gu, D Day, 94,76 square meters and publicly announced the public perusal

E submitted a written opinion to the Incheon Metropolitan City Urban Development Headquarters on March 20, 201, stating that “The land in this case was purchased for the construction of a new commercial building, but the land substitution area is too narrow and thus it is impossible to newly build a commercial building, so the land substitution area is 860 square meters.” The land substitution area of the G was planned to be 525 square meters (365.2 square meters of right area, 159.8 square meters of excessive area) of the I 493 square meters of land (hereinafter “each of the above land”).

The head of the Incheon Metropolitan City Urban Development Headquarters shall require E's above increase land substitution

After accepting the office and changing part of the land allotted by the authorities in recompense for development outlay into 860 square meters (right area 357.2 square meters, excessive area 502.8 square meters), the land substitution area was changed to 860 square meters (the land substitution area is 357.2 square meters, excessive area is 502.8 square meters), and on May 2, 2001, the land substitution

(S) The Incheon Metropolitan City Urban Development Headquarters announcement L. The land prior to the instant land substitution had been sold to Dongjin Co., Ltd. on April 1, 2003, and each ownership transfer registration was completed on May 30, 2005 by M on September 21, 2009 to the Plaintiff (the Plaintiff’s mutual “stock company and prosperity”) on June 7, 2010 in the auction procedure following the voluntary decision on commencement of auction on September 21, 2009, and the ownership transfer registration was completed in the Plaintiff’s name on the same day.

The head of the General Construction Headquarters of Incheon Metropolitan City (formerly changed: the head of the Urban Development Headquarters) shall complete the land readjustment project in this case, and on March 31, 201, publicly notify the disposition of replotting, the contents of which are new lot numbers, land categories, size, cadastral map confirmation, decision of liquidation amount, etc. by each parcel, and publicly notify B of the

arrow