logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 의정부지방법원 2017.11.08 2017나204859
조성공사비 잔대금 청구의 소
Text

1. The defendant (Counterclaim plaintiff)'s appeal is dismissed.

2. The costs of appeal are assessed against the Defendant-Counterclaim Plaintiff.

purport, purport, and.

Reasons

1. Facts recognized;

A. On September 25, 2009, the Plaintiff entered into an agreement with the Korea PPP Industry Cooperatives (hereinafter “PP Cooperatives”) on the cost of site creation works to establish a housing site to establish a housing site in the 9-3 area in the PPPP PPP Complex in the PPP (hereinafter “instant land”). The Plaintiff entered into an agreement on September 25, 2009 with the Korea PPP Industry Cooperatives (hereinafter “PP Association”).

B. After the conclusion of the sales contract for the instant land, the Plaintiff and the law firm partnership entered into an implementation contract on December 22, 2009 with respect to the Housing Site Development Corporation (hereinafter “instant construction”). However, around the end of 2010, the said implementation contract was modified into a consulting contract (hereinafter “basic contract”). The basic contract became a direct party to the contract in addition to the Plaintiff and the law firm partnership, and its major contents are as follows.

Article 1 (Public Corporation Site) (1) of the Basic Contract: The access road of 3,140 square meters (11,910 square meters) for 3,140 square meters (9,910 square meters) for 3,140 square meters for 3,140 square meters for 3,140 square meters for 3,140 square meters for 3,140 square meters for 3,140 square meters for 2, B (the plaintiff in this case refers to the plaintiff in this case) shall be paid in advance on the site of the Corporation, and the related authorization and permission shall be obtained so that the factory may be established, and the civil works, electricity, and waterworks shall be installed, and it shall be transferred to A.

Article 3 (Business Period) B shall complete the site contract and the construction work for the Corporation from the date of conclusion of the contract until November 30, 201.

Provided, That the delay in construction due to the authorization and permission problems shall be adjusted within a reasonable scope.

Article 4 (Area to be Supplied and Unit Price) The defendant, etc. will be supplied by B with the total area of the site of the Corporation in the amount of KRW 12,960,000,000,000.

Article 7 (Construction of Site) (1) B shall obtain approval for the new construction of a factory in the project site before the commencement of civil engineering works.

C. On November 24, 2010, the Pakistan publicly announced the decision to designate a district unit planning zone as to the instant land.

The plaintiff is a law firm partnership.

arrow