(영문) 수원지방법원 2020.11.19 2019가합25663
공사대금
Text

The defendant 90,267,320 won to the plaintiff A, 115,50,000 won to the plaintiff corporation B, and 17,512,000 won to the plaintiff C and each of the above.

Reasons

(2) On April 13, 2018, the Plaintiff and the Plaintiff entered into a contract with the Plaintiff to subcontract construction cost of KRW 457,600,000 (including additional tax) (hereinafter “instant subcontract”).

The contents of the standard subcontract agreement (No. 4, hereinafter referred to as the "instant subcontract agreement") prepared with respect to the instant subcontract are as follows:

A Standard Subcontract Form (Certificate 4): The name of the contractor for the E Urban Development Project Association: Installation of an outstanding storage tank in the E Urban Development Project;

2. The name of subcontracted project: Type of business registered for subcontracted project among projects for the installation of excellent storage tanks in an urban development project:

3. Construction site: The F0 won of the wife population in Gyeonggi-do;

4. Period of construction: December 31, 2018, the completion of construction on April 16, 2018.

5. Contract amount: The value of supply in the daily gold bullion 457,600,000 won (including 457,600,000) : the daily gold bullion (including 416,00,000) / [labor expenses / the value-added tax on labor expenses under the provisions of Article 84 of the Enforcement Decree of the Framework Act on the Construction Industry / the daily gold KRW 416,000,0000: the contract amount before changing the daily gold bullion 41,60,000,0000 won (including 41,60,000,000): the daily gold :

6. Payment of the price;

(a) No advance payment;

(b) Payment for completed portion: (1) Payment within 2 days after receipt of the contractor, in the same manner as the terms and conditions of the ordering person;

(1) Payment is made within 15 days from the date the project owner receives an adjustment in accordance with the details and ratio of the adjustment within 30 days from the date the project owner receives such adjustment;

7. D GH IJ L L NKO on April 13, 2018, which was omitted;

B. Plaintiff A re-subcontracted part of the instant soil work to Plaintiff B (hereinafter “Plaintiff B”) and C, and the Plaintiffs commenced the instant soil work around April 16, 2018.

C. Around June 29, 2018, the instant association established the site office after the completion of the retention construction work.