1.The part against the defendant in excess of the amount ordered to be paid under the following among the judgments of the first instance, shall be revoked:
Reasons
1. With respect to this part of the basic facts, the reasons stated by this court are as follows, and this part of the basic facts are cited by the judgment of the court of first instance pursuant to the main sentence of Article 420 of the Civil Procedure Act.
In Part 4, the following shall be added under Part 6 below, and the "relevant Regulations" shall be read as "relevant Regulations."
A person shall be appointed.
D. According to the standard pumum of the construction works in 201, including the process of calculating the estimated price of the instant construction works, etc., the unit price of soil transport construction works in the unit of cost per hour of dump trucks divided the sum of material cost, labor cost, and expenses into the daily work volume per hour. Specifically, the daily work volume per hour is the value calculated by dividing the labor volume that can transport dump trucks from the one-time round to the one-time work volume by the number of hours required to return.
In such cases, the time required to shut back (one set) is the time required to load (t1), transport (t2), cargo (t3), enter the intended place (t4), open and dismantle (t5) in accordance with the order of work.
In the calculation of the project price, the construction works of the Chungcheongnam-do Urban Development Project had a total of six sections, and the construction works of this case were implemented in the construction works (1-1). In the calculation of the project price, 4 sections of the remaining sections of the construction works (1-3), (2-1), (2-2), and (2-3) are calculated as construction cost by using the transport of soil transport construction and loaded cargo as a single item of cost, and (3-2) sections of the construction work are calculated as actual construction cost, as the type of soil transport construction work is (1-1) and the loaded cargo is calculated as construction cost.
2. Judgment on the claim for the adjustment of the contract amount due to the change of design
A. Among the Plaintiff 1’s assertion by the parties, the “soil” includes “soil transport works,” and the time when the site descriptions, bill of materials, design budget, etc. provided by the Defendant include “to transport soil and sand 2” among the types of work to be included in the soil transport work.