(영문) 서울중앙지방법원 2016.07.14 2015가단186329
양수금
Text

1. The Plaintiff:

A. 31,000,000 won and 31,000 won

B. The above case is jointly and severally with the defendant Park Jong-chul.

Reasons

1. Facts of recognition;

A. Busan Mutual Savings Bank, Inc., filed a lawsuit claiming acquisition amount against Defendant Gyeong, A, B, C, and Non-Party E by Busan District Court Decision 2005Gahap5099, which was sentenced on October 12, 2005 and became final and conclusive on November 12, 2005.

Of the above money jointly and severally with the Plaintiff, Defendant A shall be paid 264,016,632 won, Defendant E and B shall be 89,417,380 won, Defendant C shall be 40,600,000 won, and 20% interest per annum from August 3, 2005 to the date of full payment.

B. On November 23, 201, the Plaintiff’s decision on contract transfer by the Financial Services Commission.

The claim described in the subsection has been succeeded.

C. On June 23, 2013, E died, and F and G, who are children, renounced inheritance, Defendant D, the wife, solely inherited, and received an inheritance limited recognition judgment from Suwon District Court Decision 2013Modan502.

[Ground of recognition] Unsatisfy, entry of evidence A1 to 3, purport of the whole pleadings

2. According to the above facts of recognition, the plaintiff who claimed only a part of the claim amount against the defendants, and the defendant Sejong is obligated to pay damages for delay at the rate of 20% per annum from August 3, 2005 to the day of full payment with respect to each of the above amounts, jointly and severally with the defendant Eul, 31,000,000 won, defendant Eul, 9,000,000 won, defendant Eul, 31,000 won within the scope of the property inherited from the network E, and defendant Eul, 5,000,000 won, and 20% per annum from August 3, 2005 to the day of full payment.

3. According to the conclusion, the plaintiff's claim is accepted on the ground of the reasons.