Text
1. The defendant shall pay 7,495,000 won to the plaintiff and 20% per annum from September 2, 2014 to the day of complete payment.
Reasons
1. Facts of recognition;
A. The Plaintiff entered into a contract for the supply and transportation of aggregate necessary for various construction equipment at the site of "Yannam-do Small River Maintenance Works" from a limited liability company (hereinafter referred to as "Yandong-gun Construction") and applied for a payment order with the Jeonju District Court 201Hu6168 on August 18, 201, stating that the Plaintiff supplied aggregate worth KRW 77,495,00 on June 31, 201, KRW 50, KRW 54,260, KRW 800 on June 30, 201, KRW 77,62,600 on July 31, 201, KRW 77,495,00 on the aggregate of KRW 77,600 on July 31, 2011, and the said court issued the payment order with KRW 95,000 on August 18, 201.
B. Meanwhile, on August 18, 201, the Plaintiff filed an application for provisional seizure against claim with the Jeonsung District Court 201Kadan3281 (hereinafter “provisional seizure against claim”) to preserve the claim for the said construction cost, as to KRW 77,495,00 among the claim for construction cost concerning the construction cost of a small river (hereinafter “the instant construction”) against the Defendant, on the other hand, on August 18, 201, the Plaintiff filed a provisional seizure against claim with the Defendant as the garnishee, and the said court filed a provisional seizure order accepting the said claim by the Plaintiff on August 19, 2011 (hereinafter “provisional seizure against claim”). The instant provisional seizure order against claim was served on the Defendant on August 23, 2011.
C. On the basis of the above payment order, the Plaintiff filed an application for the seizure and collection order of the claim to transfer the provisional seizure of the instant claim to the principal seizure with the obligor, Defendant as the garnishee, and the claim amount of KRW 77,495,00,00 with the Jeonju District Court 2014TTY 6424. On July 28, 2014, the above court issued the seizure and collection order (hereinafter “the instant collection order”) with the content that cited the Plaintiff’s above request, and the said order was issued to the Defendant on August 1, 2014.