logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울남부지방법원 2018.09.06 2017가합112882
추심금
Text

1. All of the plaintiffs' claims are dismissed.

2. Of the litigation costs, the costs are between the Plaintiff Shin Young Construction Co., Ltd. and the Defendant.

Reasons

1. Basic facts

A. 1) Hoho General Construction Co., Ltd. (hereinafter “ Sungho General Construction Co., Ltd.”) (hereinafter “Sho General Construction”)

(2) On October 8, 2011, the Plaintiff New Line Construction Co., Ltd. (hereinafter “New Construction”) was awarded a contract for construction of the instant building (hereinafter “the instant building”) on the land other than Yeongdeungpo-gu Seoul, Seoul, and 17 lots of land (hereinafter “instant building owner”) with New Construction Co., Ltd., Ltd. (hereinafter “New Line Construction”) (hereinafter “New Line Construction”) on the following grounds: (a) on the ground of the instant construction agreement: (b) on December 8, 2011, the Plaintiff New Construction Co., Ltd. (hereinafter “New Line Construction”) entered into an agreement with the owner of the instant building 6 Co., Ltd. (hereinafter “New Construction Co., Ltd.”); (c) on the ground level 1 to 5 stories above the instant construction work; (d) on the ground level 1 to 409,000,000, and (e) on the ground level 1 to 3rd 4, 2015 new Construction Co., Ltd. (hereinafter “New Construction”).

"The name and seal was signed and sealed".

A contractor for work of this case: A contractor for work of this case and a contractor for work of this case are entering into with a contractor for work of this case and the contractor for work from November 1, 201.

arrow