(영문) 서울동부지방법원 2015.04.03 2014가합107022
공사대금
Text
1. The Defendant shall pay to the Plaintiff KRW 110,00,000 as well as 20% per annum from October 14, 2014 to the date of full payment.
Reasons
1. Claim for part of the construction cost related to civil engineering and structural construction among the construction works of the dead, dong, Hadong, and Haak apartment that was concluded with the Defendant on April 15, 2013
2. Articles 208 (3) 1 and 257 (1) of the Civil Procedure Act of the applicable provisions of Acts;