(영문) 의정부지방법원 2018.08.09 2015가단107427
공사대금
Text

1. The Plaintiff:

A. Defendant Jeong LLC, Inc., Ltd., 82,584,170 won and 7,038,262 won among them.

Reasons

1. Basic facts

A. A building construction works and subcontracting contract 1) The Plaintiff is a metal structure, window-production and installation work business, and Defendant Pream Partnership Director (former trade name: forest design loan loan, hereinafter “Defendant Company”).

(2) On August 21, 2014, the Plaintiff entered into a subcontract with the Defendant Company for the construction of metal and windows among the construction works of the Gangnam-gu Seoul building that the Defendant Company contracted, with the amount of KRW 286,00,000 (including value-added tax) and the construction period from the date of the contract for the construction to January 31, 2015.

(hereinafter referred to as “A Corporation”) Defendant Construction Mutual Aid Association (hereinafter referred to as “Defendant Association”)

(B) Around November 6, 2014, the Defendant Company guaranteed the payment of the subcontract price of KRW 286,00,000 for the construction cost of A. B. On September 16, 2014, the Plaintiff entered into a contract with the Construction Company for the Construction of Oriental Medical Hospital and the Plaintiff, who entered into a contract with the Defendant Company on September 16, 2014 (including value-added tax) for the construction contract amounting to KRW 445,00,000 (including value-added tax) among the construction works for the new construction of oriental medical complex buildings in B. C. at the time when the Defendant Company was contracted, and from the date when the contract was entered into for the construction period to January 31, 2015 (hereinafter referred to as “subcontract construction works”).

C. (1) The Defendant Company agreed to pay the construction cost after 30 days from the time of filing a claim for the payment for the completed portion at the end of each subcontract.

2) The Defendant Company: (a) paid the Plaintiff KRW 36,850,00 on November 14, 2014; (b) KRW 19,80,000 on December 1, 2014; (c) KRW 154,00,000 on December 1, 2014; (b) KRW 21,50,000 on December 30, 2014; and (c) KRW 20,000 on December 30, 2014; and (d) KRW 13,350,000 on the same day; and (g) KRW 13,350,00 on the same day; and (f) KRW 60,000 on February 16, 2015; and each of the relevant amounts shall be paid by account transfer (hereinafter referred to as “construction price”).

(d) the addition of A Project;