(영문) 제주지방법원 2015.02.06 2014가단13371
물품대금
Text

1. The Defendant shall pay to the Plaintiff KRW 72,940,90 and the interest rate of KRW 20% per annum from August 20, 2014 to the day of complete payment.

Reasons

1. On April 16, 2013, the Plaintiff entered into a contract for the supply of ready-mixeds with the purport that the Plaintiff would supply ready-mixeds at the site of Jeju Seopo-si, Seopo-si, Seopo-si, 1395, Seopo-si, Seopo-si, Seopo-si, Seopo-si, Seopo-si, Seopo-si, Seopo-si, Seopo-si, 1395. Upon the Defendant’s request, the Plaintiff supplied Lepo-mixed amounting to KRW 72,940,90 from April 10, 2013 to June 4, 2013. As such, the Defendant may be acknowledged to have agreed between the parties, or to have agreed upon the entire purport of all pleadings as stated in the evidence No. 1, 2, and 3, and the Defendant’s obligation to pay to the Defendant the amount calculated from 200% to 200% of the following day of the instant lawsuit to 2014.

In this regard, the defendant only makes an unclear argument that there is a problem in calculating the quantity of the supplied container supplied by the plaintiff, but does not present specific arguments or materials. The defendant's argument is rejected.

2. Conclusion, the plaintiff's claim is reasonable and acceptable.