Text
1. Defendant (Counterclaim Plaintiff) Co., Ltd.: (a) Plaintiff (Counterclaim Defendant)
(a) each real estate listed in the separate sheet;
Reasons
1. Basic facts
A. The land indicated in the attached list (hereinafter “instant land”) is the original F ownership, and there was an office with a size of 114.13 square meters on that ground and a warehouse building on that ground.
B. For the purpose of operating the automobile maintenance business by newly building the automobile maintenance plant on the instant land, Defendant E received the letter of acceptance from F on March 6, 1992, stating, “I consent to use all the instant land and the buildings for the automobile maintenance factory to be newly constructed by the users thereafter as the automobile maintenance factory from July 1, 1992 to July 31, 1999,” which read “I consent to use from July 1, 1992 to July 31, 199.”
Site: Building site: The term of lease under Article 2 of 114.13 square meters [a building with steel pipe slate (including office and warehouse as of around 43.59 square meters) is to be destroyed and a lessee is to construct a new building as a repair factory later] shall be between 84 months (7 years) from the date of the contract.
Provided, That the lessee may use the building built in the name of the lessor as the funds of the lessee, and the lessee may continue to use the building built in the name of the lessor after consultation even after the expiration of the contract period unless the lessor has a special use plan.
Article 6. The lessor shall prepare all documents necessary for the lessee to construct a suitable building as a maintenance factory, and the owner of the leased shall provide the lessee with cooperation to the maximum extent possible.
C. On July 1, 1992, Defendant E and F entered into a lease agreement consisting of KRW 50,000,000, monthly rent of KRW 3,000,000 with respect to the instant land and existing buildings, and the written agreement includes the following:
On August 29, 192, Defendant E obtained a construction permit to construct an automobile maintenance factory of the size of the first and second floor above the instant land by using the owner’s name F on August 29, 1992, and completed the instant building at its own expense.
With respect to the building of this case, F. 3 March 1993.