(영문) 인천지방법원부천지원 2020.10.06 2019가단8483
노무비 등
Text

All of the plaintiff's claims are dismissed.

Litigation costs shall be borne by the plaintiff.

Reasons

1. Basic facts

A. From December 2017 to September 2018, the Defendant constructed construction of landscaping facilities among E-Housing Reconstruction Works in Ansan-gu, Ansan-si.

F performed duties as a field agent at the construction site of the above landscaping facility.

B. From among the details of unpaid wages, each of the labor workers indicated in the “name” column (hereinafter “the instant labor workers”), and the remaining labor workers except the Plaintiff among the instant labor workers (hereinafter “the remainder of the instant labor workers”) entered into a construction contract (hereinafter “the instant construction contract”) with the Defendant around July 2018, stating that “the instant labor workers shall perform construction works on news bubbles (hereinafter “instant construction”) among the construction works in the landscaping facility under the foregoing paragraph (a) and in return, the Defendant shall be paid KRW 6,000 per square meter of the construction area (hereinafter “the instant construction contract”).

C. After completing the instant construction work, the instant labor personnel agreed with the Defendant on November 15, 2018, and “The instant labor personnel agree to settle the construction cost of 62,100,000 square meters for the construction cost of 10,350 square meters for the primary construction area of the instant construction contract (prepaid on August 31, 2018) and the secondary construction area of 7,334 square meters for the construction cost of 44,004,000 square meters for the primary construction area of 10,104,000 square meters for the said settlement (hereinafter “instant settlement agreement”).

After that, on August 31, 2018, the Defendant paid the Plaintiff the construction cost of KRW 62,100,000 for the above construction area of the first installment (hereinafter “the first installment”) and ② on November 23, 2018, the construction cost of KRW 44,004,00 for the above second installment (hereinafter “the second installment construction cost”).

The Plaintiff, the team leader, entered into the instant settlement agreement on behalf of the remaining labor parties, which are the team team recruited by the Plaintiff, and received the first and second installment construction cost from the Defendant.

【Legal basis for recognition】