Text
1. The Defendant’s KRW 72,90,155 as well as the Plaintiff’s annual rate of KRW 5% from October 2, 2013 to November 2, 2016.
Reasons
1. Basic facts
A. On April 2011, the Defendant assumed office as the representative director of the Plaintiff and served as the representative director of the Plaintiff until his dismissal on August 9, 2012.
On May 11, 2012, the construction cost of the temporary project owner (cost) of the commercial building development project, including subway No. 4, subway No. 5,000,000, such as the walls of the commercial building in the subway No. 4, subway No. 302-10, Jul. 2, 2012, 2012, which is unclear in the middle of July 7, 2012, the construction cost of the project owner, which is not known to the operator of the commercial building No. 202-10, 200, the construction cost of the commercial building No. 202-10, 200.
B. The Plaintiff, the purpose of which is the indoor building construction business, concluded a construction contract for the interior of subway stores as indicated below (hereinafter “each of the instant construction contracts”).
C. On July 26, 2012, the Defendant filed a complaint from the Defendant’s wife F (former representative director G, who was appointed as the Plaintiff’s inside director on September 16, 201) for the crime of adultery, and was sentenced to the Defendant’s imprisonment for six months and two years of suspended execution at the Seoul Eastern District Court on October 29, 2012, and the said judgment became final and conclusive on November 6, 2012.
The defendant was contracted to the plaintiff.
The construction contract stated in paragraph (1) is re-contracted in the name of H which the defendant was involved in the management while using the office of representative director or director as stated below and received the payment for the construction work.
On July 28, 2012, the date of the payment of the construction price (the original account) on the date of the temporary owner’s payment (the original account) and the sum of 3,700,000,000 H H August 13, 2012, 30,700,000 on August 30, 2012, 30, 30,000 H H on August 30, 2012 H on September 37, 200, 200, 300,000 H on September 37, 2012, 200, Hadia on July 30, 200, 198; Act No. 630,000,000, 1000,000 or more; Act No. 63043, Aug. 23, 200; Act No. 63030, Oct. 4, 2004
E. The defendant, as the representative director of the plaintiff, has a duty to implement and maintain the contract concluded by the plaintiff and faithfully manage the funds in the name of the company in order to avoid causing damage to the company.