Text
1. The Defendant shall pay to the Plaintiff KRW 31,350,000 and the interest rate of KRW 15% per annum from December 23, 2016 to the date of full payment.
Reasons
1. Facts of recognition;
A. The Plaintiff concluded a subcontract with the Defendant around May 2015, as a contractor for the metal construction of the Kug Incheon Logistics Center, and entered into a subcontract with the Defendant.
The construction cost was agreed at 12,00,000 won (excluding value-added tax).
B. The Plaintiff entered into a subcontract around September 2016 with a contract with the Defendant for metal construction at the central point of inspection team of Hyundai Motor Vehicles.
The construction cost was agreed at KRW 16,500,000 (excluding value-added tax).
C. The plaintiff completed the above construction work.
[Reasons for Recognition] Each entry of Gap evidence Nos. 1 through 4, the purport of the whole pleadings
2. According to the above facts of recognition, the Defendant is obligated to pay to the Plaintiff the total construction cost of KRW 31,350,000 including value-added tax, as well as damages for delay calculated at the rate of 15% per annum from December 23, 2016 to the date of full payment, which is the day following the day on which the copy of the complaint of this case was served to the Defendant, as sought by the Plaintiff.
3. The defendant's assertion that the defendant did not receive the warranty insurance policy, but there is no evidence to acknowledge it, and the payment of construction price cannot be refused solely on the ground thereof.
Although the defendant asserts that there is a defect in construction, there is no evidence to acknowledge it.
We do not accept the defendant's argument.
4. To accept the Plaintiff’s claim for conclusion