(영문) 서울동부지방법원 2019.10.16 2019가단10164
대여금
Text

1. The Defendant’s KRW 200,000,000 as well as 4% per annum from July 29, 2017 to August 5, 2019, respectively, to the Plaintiff.

Reasons

1. The description of the grounds for the claim shall be as specified in the attached Form;

2. Judgment without holding any pleadings (Articles 208 (3) 1 and 257 (1) of the Civil Procedure Act);

3. Pursuant to the provisions on statutory interest rate under the main sentence of Article 3(1) of the Act on Special Cases concerning Expedition, etc. of Partial Dismissal Lawsuit (amended by Presidential Decree No. 29768, May 21, 2019 and enforced June 1, 2019), the portion exceeding the damages for delay calculated at the rate of 12% per annum from the day after the copy of the complaint is served to the day of complete payment, among the Plaintiff’s damages for delay, exceeds the damages for delay

(However, in applying Article 98 and the proviso of Article 101 of the Civil Procedure Act, the defendant shall bear all the costs of lawsuit).