(영문) 인천지방법원 2015.11.20 2014가단30796
금형제작대금
Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Recognizing facts, the following facts do not conflict between the parties, or may include the following facts: Gap evidence 1 to 3, evidence 5-1, 6-2, Eul evidence 2-2-2, Eul evidence 1, 2, 3-8, and 10-1, 2, and 13-2, and 10-1, 2, and 13-3, the witness Eul's testimony, part of the witness C's testimony, the results of this court's CD verification, the results of the fact inquiry into DNA.

The plaintiff is a corporation that mainly carries on gold-type manufacturing business with the trade name of "D", and the defendant is a corporation that installs and sells card terminals.

B. On March 15, 2012, the Plaintiff entered into a contract with the Defendant with the content that the Plaintiff would produce and deliver AD-P card type (a digital signature device using the 7-person L CD monitor and the tampboard; hereinafter “instant device”) (hereinafter “instant gold type”) (hereinafter “instant contract”).

Article 2. The definition of the duties and the result shall be produced and supplied to the defendant within the payment period specified in Article 6 of this Agreement as the letter approved by the defendant.

Article 4. Gold-type production costs: 91,660,00 won (excluding value-added tax): 4,5830,000 won (excluding value-added tax): Any balance that is paid within three days after the conclusion of the contract: 4,5830,000 won (value-added tax separate) shall be paid within seven days after the completion of all the business defined in Article 2 of this Agreement and the delivery of the plaintiff's results to the defendant, and the defendant and E (the company in charge of the instant terminal design) shall be paid within seven days after the final approval.

Article 6 1: Final current events on May 3, 2012 (e.g., gold-type production and the first current events): On May 10, 2012, the Plaintiff, at the place determined by the Defendant, shall be subject to inspection and gold-type inspections in accordance with the inspection standards conducted by the Defendant and E, and the Plaintiff, at the place determined by the Defendant, shall be sentenced to gold-type inspections.