Text
1. The defendant shall be the plaintiff.
A. On October 15, 2012, the 2,5,6,8 parcels of 55-22 No. 55-22 at the port of Pakistan-si, which was concluded with the Plaintiff.
Reasons
I. The following facts, in the progress of the case, are recognized to the effect that there is no dispute or the entire pleadings, other than the macrodic evidence.
1. On October 15, 2012, the Plaintiff entered into a contract with the Defendant for the new construction of the building for the ground-based factory on the face-based land (5-22, and five parcels of land), among the new construction works of the Defendant and the said new construction works, ① 9,10 parcels of land, ② 2,5,6, and 8 parcels of new construction works among the new construction works of the 2,5,6, and 8 parcels of land (hereinafter referred to as the “instant subcontracting corporation”).
[A] The construction period on October 15, 2012 to June 30, 2013 (including the last extension of the construction period under the above paragraph (2) to June 30, 2013) was set during the construction period from October 15, 2012 to June 30, 2013; with respect to each of the materials of the panel at the time, an agreement was made to use the “Outer Party Panel EPS 100T, the roof Panel EPS 200T, and the Partitioned Panel EPS 50T (hereinafter collectively referred to as the “instant panel”) as follows:
[A 1, 2] 3. Otherwise, the warranty period of the panel construction of this case was agreed as "two years" respectively.
[A 1 and 2] 4. The Defendant was supplied with a panel with the test report stating that “the instant panel meets the standards for noncombustible materials as notified by the Ministry of Land, Transport and Maritime Affairs No. 2012-624, the Ministry of Land, Transport and Maritime Affairs,” which is the supplier of the instant panel, and executed it at the site of the instant panel.
[3] 5. The Defendant completed the instant panel construction on June 5, 2013 and June 30, 2013.
[6] 6.6. The plaintiff did not pay the subcontract price, the defendant filed a lawsuit against the plaintiff as the Incheon District Court 2014Kadan8058, etc. and drafted the same agreement as the attached Form on April 11, 2014.
(A) On September 7, 2014, the Plaintiff’s compliance with the “A” 100 meters from the instant panel executed by the Defendant at the Korea Construction Environment Examination and Research Institute on September 23, 2014.