(영문) 춘천지방법원속초지원 2015.11.17 2015가단2463
물품대금
Text

1. The Defendant’s KRW 35,736,195 and interest rate of KRW 15% per annum from June 2, 2015 to the date of complete payment.

Reasons

1. The Plaintiff, which caused the claim, supplied the Defendant with building materials (e.g., presses, reflectrs, and miscellaneouss) equivalent to KRW 39,205,925 from November 22, 2012 to April 18, 2015, and received reimbursement from the Defendant only KRW 3,469,730.

Therefore, the defendant is liable to pay to the plaintiff the remainder of the goods price of KRW 35,736,195 and damages for delay.

2. Judgment made by the confession of applicable provisions of law (Article 208 (3) 2 of the Civil Procedure Act, and the defendant only submitted a formal written objection with the certified copy of the payment order and the formal written objection, and the subsequent failure to attend the court on the date of pleading without submitting a specific written response, it shall be deemed that all of the plaintiff's allegations have been led to confession under Article 150