logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울중앙지방법원 2016.07.19 2015가합573296
부당이득금
Text

1. The plaintiffs' primary and conjunctive claims are all dismissed.

2. The costs of lawsuit are assessed against the plaintiffs.

Reasons

1. Basic facts

A. In relation to Plaintiff A’s land ownership, Plaintiff A is the owner of 132,397 square meters of forest land in Gwangju City, and Plaintiff B is the owner of 32,209 square meters of forest land in Gwangju City.

(hereinafter referred to as “each of the above lands Nos. 1 and 2”

(1) On February 26, 1985, the Defendant completed the registration of creation of superficies with respect to the land of this case on the ground of the contract to establish superficies as of February 26, 1985, No. 3470, the Suwon District Court, Sungnam-Support Registry, which received on December 24, 1984: The Defendant’s superficies: The purpose: The period of superficies: the period of the construction and ownership of steel towers and transmission lines: the special agreement for the period of existence of steel towers and transmission lines: the total land rent of KRW 616,074 shall not be paid at one time, and the rent shall not be increased during the duration of superficies. The land of this case includes rent following the construction and ownership of transmission lines at the space on the land of this case. (2) The Defendant completed the contract to establish superficies with respect to the land of this case on November 24, 1984 as the “Defendant’s establishment of superficies” under the special agreement between Sungnam-nam Branch Branch of the Gwangju District Court, which received from P.

C) From the date of each of the instant superficies contract, the Defendant installed a special high pressure processing transmission line on the land and the airspace above each of the instant land and manages it up to the present day. The size of the steel site and the space above each of the instant land is as indicated in the attached Tables 2 and 3. D. The market price of the steel tower among each of the instant land is KRW 2,642,250 (the first land, KRW 271 square meters), KRW 2,50,60 (the market price of the steel tower is KRW 2,642,250 (the first land, KRW 271 square meters), and KRW 2,50,00 (the second land, and KRW 218 square meters) as of the date of conclusion of the contract. The market price in each of the instant land is March

arrow