Text
1. The Defendant’s KRW 7,00,000 as well as the Plaintiff’s annual rate of 5% from September 5, 2017 to December 12, 2019.
Reasons
1. Basic facts
A. From June 5, 2001, the Plaintiff engaged in the food manufacturing business, etc. with the trade name “E” from Asan City from around June 5, 2001, and on June 2, 2008, the Plaintiff is a person engaged in the food manufacturing business, etc. on the trade name “E”. On June 2, 2008, the Plaintiff is a person engaged in the food manufacturing business, etc. on the part of Asan City Fasi-si 2,232 square meters adjacent
(2) Around September 13, 2013, the Plaintiff purchased the instant land and completed the registration of transfer of ownership in his/her name. (2) Around September 13, 2013, G purchased a new construction permit to build a 517.71 square meter (one unit of H company) of a 1st floor of the general steel structure framed branch, one-story branch, and one-story factory on the instant land, and contracted its new construction to I Co., Ltd.. (K Co., Ltd., Ltd., Ltd., and hereinafter “J”) to suspend the construction and complete the remaining construction, and obtained approval for use on May 20, 2016.
(3) On June 7, 2016, G, on the instant land, the land category of the instant land was changed to a factory site for the factory, and G, upon obtaining permission for each extension of 26.6m2 square meters for one floor of a factory (free storage) of the light steel structure 67.62m2 (free storage) and one story of the light steel-frame structure 26.6m2 (three m3 m2) on each floor, after completing construction with permission for each extension of 26.6m22, July 22, 2016 (hereinafter the above paragraphs (2) and (3) (hereinafter the above paragraphs).
[4] Meanwhile, around September 6, 2013, the Plaintiff’s spouse L was granted a building permit to newly build a factory (waste collection center) of 1,950 square meters on the one-story of the general steel structure 1,950 square meters (H company 1), ② one-story of reinforced concrete structure (construction room), 30.69 square meters (2 Dong of H company), ③ 66 square meters for one-story of the light steel-frame structure 3, 66 square meters (3 Dong of H company), and 24 square meters for the light steel structure 24 square meters (waste collection center) on the other hand, and completed the construction report on September 16, 2015.
(hereinafter referred to as “third factory”). L L around August 2016, around 2016, is KRW 500 million for the construction cost of the third factory construction project to P Co., Ltd. (excluding value-added tax and construction period).