Text
1. The defendant shall be the plaintiff.
A. Of the land size 269.8 square meters in Kuju-si, the attached drawing 25, 26, 27, 28, 29, 30, 6, 7, 8, 9, and 25 shall apply.
Reasons
1. Basic facts
A. The Plaintiff is an owner who completed the registration of transfer of ownership on June 3, 2014 with respect to E Dae-si 103.1 square meter, and completed the registration of transfer of ownership on June 3, 2014, with respect to the registration of transfer of ownership, c. 269.8 square meter in Kuju-si, and d. 70.1 square meter in Kuju-si, respectively.
(hereinafter the above three parcels are combined to “the land owned by the Plaintiff of this case” (hereinafter “instant three parcels”). B.
The Defendant is the owner who completed the registration of ownership transfer on February 21, 1983 with respect to the land owned by the Defendant (hereinafter “instant land”) and its ground (hereinafter “instant building”).
C. The building of this case is not only the land owned by the Defendant, but also the land owned by the Plaintiff, such as the attached Form No. 5, and the attached Form No. 7, which are the land owned by the Plaintiff.
In order to reach a contribution from the land owned by the Plaintiff and the land owned by the Defendant of this case, the land owned by the Plaintiff of this case must pass through the original city J land (land category: road).
Attached Form
(8)The part and the attached Form (b) are used as a passage leading to a contribution after passing through the original cityJ land from the land owned by the Plaintiff and the land owned by the Defendant of this case.
However, the defendant is arguing that the part on the ship connecting 19,36,37,38 of the attached Form (2) does not pass through.
(e) means the left side of the J land on the basis of a drawing on the left side of the land at Won-ju;
In the case of the Plaintiff’s land, F. F. 573 square meters is located, and the Plaintiff completed the registration of ownership transfer as to the shares on February 19, 201, and on December 15, 2002, the Plaintiff completed the registration of ownership transfer as to the shares on December 15, 2005.
On the right side, K is located at the prime city.
There is a signboard owned by the Defendant ("G") between the building constructed on the F land of the original city and the building constructed on the K land of the original city of the original city of the original city of the Republic of Korea, and the signboard owned by the Defendant ("G") is installed.
[Reasons for Recognition] Gap evidence Nos. 1 through 6, Eul evidence Nos. 1 and 3, and this Court's appraiser L.