Text
1. The Defendant (Counterclaim Plaintiff) paid KRW 28,265,400 to the Plaintiff (Counterclaim Defendant) and its related amount from October 30, 2018 to December 4, 2018.
Reasons
A principal lawsuit and a counterclaim shall be deemed simultaneously.
1. Basic facts
A. On June 9, 2015, the Plaintiff and the Defendant concluded a contract for construction works (hereinafter “instant contract”) with respect to D and two parcels of land (hereinafter “instant construction works”), setting the construction cost of KRW 110,000,000, and the construction period from June 15, 2015 to December 5, 2015.
B. After completing the instant construction work, the Defendant received the completion inspection from the Tong-si on December 3, 2015.
C. The Plaintiff paid KRW 80,000,000, out of the construction cost of KRW 110,000 according to the instant contract, to the Defendant; on April 20, 2016, the Plaintiff prepared a written statement of performance of the construction cost that “the remaining construction cost of KRW 30,000,000 shall be paid by July 31, 2016,” and issued it to the Defendant.
【Ground for Recognition: Facts without dispute, Gap evidence 1, Eul evidence 1 and 2, and the purport of the whole pleadings】
2. Determination on the main claim
A. Since there was a defect such as modification of a stone shed, etc. in relation to the instant construction project, the Defendant is obligated to pay 35,189,150 won and damages for delay to the Plaintiff in lieu of defect repair.
나. 판단 1) 갑 제1호증, 제2호증의 1 내지 45의 각 기재 또는 영상, 감정인 E에 대한 감정촉탁결과 및 변론 전체의 취지에 의하면, 이 사건 공사와 관련하여 아래 표 기재와 같이 축대(조경석) 변형 등의 하자가 발생하였고, 위 하자의 보수비용이 합계 28,265,400원임을 인정할 수 있다. 순번 하자 항목 및 보수 내용 보수비용(단위: 원) 1 축대(조경석) 변형 12,633,440 2 영산홍 식재 부족 및 고사 3,157,600 3 축대 변형에 따른 담장(휀스) 재시공 8,604,120 4 조경수(넝쿨장미 부족 및 고사 3,183,070 5 배관 및 스프링클러 누수 등 687,170 하자보수비용 합계: 28,265,400원 이와 관련하여 피고는, 조경석의 경우 당초 3m 높이로 쌓기로 하였는데...