Text
1. All of the plaintiffs' claims are dismissed.
2. The costs of lawsuit are assessed against the plaintiffs.
Reasons
1. Basic facts
A. 1) The Plaintiffs entered into a contract for construction works (hereinafter “instant construction works”) among the “C development projects” ordered by the Defendant.
(2) The Plaintiffs concluded the first and several contracts with the Defendant for the contract amounting to KRW 4,874,00,000, and the construction period from December 16, 2014 to December 31, 2015 (hereinafter “each of the instant contracts”) with respect to the instant construction works on December 10, 2014 after being selected as a successful bidder in the said bidding, and participated in the bidding. The Plaintiffs entered into the instant contracts with the Defendant for the first and several contracts for each of the instant contracts (hereinafter “the instant contracts for the construction of the instant number,” and “the instant contracts for the construction of the instant number,” and “the instant contracts for each of the following contracts,” and “the total period from the date of the completion of the construction, December 4, 2016,” respectively.
(3) After the amendment of the agreement on total construction cost and total construction period, the Plaintiffs and the Defendant concluded the instant two and three contracts, respectively. The period of construction of the instant two and three contracts from October 5, 2015 to August 31, 2016. From June 1, 2016 to November 30, 2016, the Plaintiffs and the Defendant concluded the instant three and three contracts to ensure that part of the construction period overlap. (b) While the developments leading up to the conclusion of the instant four and three contracts and the filing date of the application for adjustment of construction amount of the Plaintiffs, the Defendants and the Defendant concluded the instant contracts on December 4, 2016, the date of completion of construction of construction of the instant two and three different contracts, the date of completion of construction of construction of the instant two and the date of completion of construction of construction of the instant contracts can not be expected to have been able to have been able to be able to be able to be able to be able to be able to be able to be able to be 16,0.16.
2 The Plaintiffs were due to the Defendant’s failure to secure the budget on November 21, 2016.