Text
1. The Defendant shall pay 2,8820,000 won to the Plaintiff and 20% per annum from March 10, 2015 to the date of complete payment.
Reasons
1. Comprehensively taking account of the overall purport of Gap evidence Nos. 1 and 2 as to the cause of the claim, the defendant was issued a summary order of KRW 1 million at the Dong branch of the Daegu District Court on January 4, 2006, and the defendant was issued a summary order of KRW 1 million at the time of fraud, etc. (Article 4743), which became final and conclusive as is, around August 105, 2005, by preparing a loan agreement (Article 1(1)1) with respect to the loan agreement with the plaintiff around August 10, 205, even though the plaintiff was unable to make a normal payment for the credit amount in spite of the plaintiff's failure to pay the credit amount normally.
Therefore, the Defendant is obligated to pay to the Plaintiff damages for delay calculated at the rate of 20% per annum from March 10, 2015 to the day of full payment, which is obviously a day after the delivery of a copy of the complaint of this case sought by the Plaintiff as a result of the tort.
2. The defendant's assertion that the defendant did not receive a loan from the plaintiff and did not prepare and deliver the loan agreement. However, in light of the final summary order and the statement in the loan agreement, the above argument is rejected.
3. In conclusion, the plaintiff's claim of this case is reasonable, and it is so decided as per Disposition.