Text
1. Of the distribution schedule prepared by the above court on June 14, 2019 with respect to the distribution procedure A case of the Seoul Central District Court, the defendant is the defendant.
Reasons
1. Basic facts
A. The Plaintiff’s claim 1) The Plaintiff Company B (hereinafter “B”).
(2) The Plaintiff filed a lawsuit against B and C seeking reimbursement of KRW 25,429,461, and KRW 20,000,000 on November 10, 2017, respectively, on June 28, 2016, with a credit guarantee agreement with a representative director C, and pursuant to the said agreement, the Plaintiff filed a lawsuit seeking reimbursement against B and C, and the judgment became final and conclusive around August 31, 2018, stating that “B and C jointly and severally paid to the Plaintiff 258,362,99, and KRW 245,64,242 from June 28, 2016 to September 5, 2016, and KRW 10% per annum from the next day to the date of full payment.”
(Seoul Central District Court 2016Gahap549627).(b)
1) The Plaintiff is entitled to file a lawsuit seeking revocation of fraudulent act, etc.
) The sales contract concluded on May 3, 2016 (hereinafter “instant sales contract”) was concluded.
(2) On November 29, 2018, the court revoked the instant sales contract within the scope of KRW 166,550,384 by filing a lawsuit to revoke it on the ground that it is a fraudulent act. E pays to the Plaintiff 166,550,384 won with the annual interest rate of KRW 5% per annum from the day following the date the instant judgment became final and conclusive to the day of full payment, and the judgment became final and conclusive around that time. (2) On November 29, 2018, the court revoked the instant sales contract within the scope of KRW 166,550,384 with respect to the instant real estate by the Defendant in the lawsuit to revoke the fraudulent act. E paid to the Plaintiff the amount calculated at the rate of KRW 5% per annum from the day following the day the instant judgment became final and conclusive to the day of full payment, and the judgment became final and conclusive around that time.
(Seoul Northern District Court 2017Kadan114945, 3) On the other hand, on November 26, 2016, on the real estate in this case, the auction procedure of real estate was commenced on November 26, 2016 (Insuwon District Court FF, hereinafter referred to as "the real estate in this case").