logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 전주지방법원 2017.10.19 2016가합1730
약정금
Text

1. Defendant C shall pay the Plaintiff KRW 23,00,000 and the interest rate of KRW 15% per annum from June 11, 2016 to the date of full payment.

Reasons

1. Basic facts

A. The conclusion of each construction contract between the plaintiffs and E 1) The plaintiff limited company A (hereinafter "Plaintiff A").

A. E Co., Ltd. (hereinafter “E”) on April 9, 2009

between the former and F.N. G construction project on the ground of six parcels outside F.S. in the previous city (hereinafter referred to as “instant new construction project”).

(2) On October 15, 2009, Plaintiff B entered into a standard subcontract for the construction work with E to supply and demand the 572,000,000 won of the contract amount, and completed the electrical construction work under the said contract. (2) On October 15, 2009, Plaintiff B entered into a standard subcontract for the construction work with E to supply and demand the 96,800,000 won of the cost of the instant newly constructed construction work.

Plaintiff

B The construction work was completed under the above contract, but only 50,000,000 won out of the construction work was paid and did not receive the remainder of 46,80,000 won.

B. E’s lien verification E drafted, on July 20, 2010, at No. 2767 of the Ministry of Justice H General Law Office, etc., a notary public drafted a certificate with the following content (hereinafter “instant certificate”).

Confirmation of lien and a statement of discharge of obligation

1. On May 4, 2010, all 23 suppliers and material suppliers attend a meeting of creditors of the Corporation at the corporate office of the debtor and appoint the representative of the claim group as the representative of the claim group, and until the debtor company’s board of directors appointed on July 19, 2010 as the representative of the claim group at the time the debtor company’s board of directors approved on July 19, 2010 (2,474,019,000 won (2,474,019,000) of the obligation for the construction cost approved by the corporate board of directors of the debtor company was paid to the entire building (as indicated in the table).

2. The debtor acknowledges that (1) the representative director J, (2) K, and (1)L representative director M has accepted the right of retention and debt payment from the creditors concerned with lien holders and the right of retention in possession of the building with due care.

arrow