(영문) 서울중앙지방법원 2017.03.15 2015가합415
손해배상 등
Text

1. As to the Plaintiff’s KRW 361,511,655, and KRW 101,00,000 among them, the Seoul Housing Corporation shall:

Reasons

1. Basic facts

A. Status 1 of the parties concerned) The Plaintiff is the Jung-gu Seoul Metropolitan Government A apartment (hereinafter “instant apartment”).

(2) For the management of the 15-dong 15-dong 15-dong 1,326 generations (general 359 households for sale in lots, public 967 households), the Plaintiff (appointed parties) and the list of the designated parties and the “selected” of the requested amount by the designated parties are the parties to the sales contract for the general public among the apartment buildings in this case.

3) Defendant Corporation is a project proprietor who constructed and sold 359 households among the instant apartment units, and the Intervenor joining the Defendant (hereinafter “ Intervenor”).

2) The Intervenor and Hyundai Construction Co., Ltd. (hereinafter “Modern Construction”) together with the Intervenor and Hyundai Construction

(B) The Defendant Construction Mutual Aid Association is a company that jointly performed the instant apartment construction by being awarded a contract with the Defendant Construction Corporation, and the Defendant Construction Mutual Aid Association is a company that has concluded each contract for the defect liability of the instant apartment with the Intervenor, etc. Around March 8, 2010, the Defendant Construction Mutual Aid Association concluded each contract for the defect liability of the instant apartment units with the Intervenor, etc. and the Defendant Construction Mutual Aid Association. Around March 8, 2010, the Defendant Construction Mutual Aid Association concluded each contract for the defect liability of the apartment units among the instant apartment units, and on December 19, 2011, replaced the guarantee creditor as the Plaintiff

(Unit) The amount of security deposit for the guarantee period from January 9, 201 to January 8, 2011 (1 year), the construction finished, electricity, landscaping, 193, 980, 292 on January 9, 2010 to January 8, 2012 (2 years), machinery, electricity, civil engineering, landscape architecture, 419,760, 037 3 from January 9, 2010 to January 8, 2013 (3 years), the designation of 69, 624, 8264 from January 9, 201 to January 8, 201, and the basis for fire-fighting, electricity, fire-fighting, fighting, 824, 8264 from January 20 to January 8, 2014; Defendant 20, 2017, 702, 10 to 319,510-6, 2018