Text
1. The Defendant’s KRW 62,00,000 as well as the Plaintiff’s annual rate from May 3, 2014 to June 12, 2015, and the following.
Reasons
1. Facts of recognition;
A. (1) On March 2013, 2013, the Plaintiff entered into the instant contract, etc.) Construction Daehan Co., Ltd. (hereinafter “DD Construction”).
(C) The construction contract was concluded between April 15, 2013 and April 20, 2013 with the purport that Daehan Construction subcontracted from Chungcheongnam Construction will complete the construction contract from April 15, 2013 to April 20, 2013 (i.e., KRW 180,000,000,000,000). As the portion of 56m of the 56m section of the re-construction is excluded from the object of construction, the construction price was set at KRW 161,935,484, while deducting the construction cost equivalent to the above 56m section from the total construction cost.
2) The Plaintiff re-subcontracted the said construction work (D 558m - 56m - 56m hereinafter “instant construction work”) to the Defendant immediately after the conclusion of the construction contract with DD construction at KRW 160 million for construction cost.
(hereinafter “instant contract”). (b)
1) The Plaintiff paid 62 million won to the Defendant upon the request of the Defendant for the preparation, etc. of the instant construction work. Furthermore, the Plaintiff’s transfer of 62 million won to the Defendant’s account book to the Defendant’s account book No. 10,000,000 on March 7, 2013, to the Defendant’s account book No. 30,000,000 on March 17, 2013, to the Defendant’s account book No. 10,000 on March 23, 2013; however, the Plaintiff’s transfer of money to the Defendant’s account book No. 10,000 on March 23, 2013 to the Defendant’s account book No. 10,000 on March 10, 2013, the Plaintiff did not assert the Plaintiff’s transfer of money to the Defendant’s account book No. 30,600,000,307.
E.