logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 인천지방법원 부천지원 2018.04.26 2016가단110880
손해배상(기)
Text

1. Defendant A Co., Ltd.: (a) KRW 99,577,500 for the Plaintiff and 5% per annum from August 6, 2016 to April 26, 2018.

Reasons

1. Facts of recognition;

A. The Plaintiff is a corporation that is engaged in planning and production of images, sound records, etc.; Defendant A (hereinafter “Defendant Company”) is a corporation that engages in the business of installing stage equipment and lighting equipment; Defendant B is a company director that is the representative of the Defendant Company; Defendant C is a director of the Defendant Company; and Defendant C is a director of the Defendant Company.

B. On December 2, 2015, the Plaintiff entered into a contract with the Defendant Company to contract for the Switzerland stage equipment and the construction of construction sound (hereinafter “instant construction”) (hereinafter “instant contract”) (hereinafter “instant construction contract”), and the main contents thereof are as follows.

1. The name of construction: E construction;

2. Principal contractor: The plaintiff/contractor: The defendant company.

3. Construction period: Value-added tax of 25,00,000 won for the supply price of 275,000,000 won on January 4, 2016, as of December 2, 2015, respectively: 25,00,000 won;

6. Payment of price;

(a) 40% in advance (20% in December 2, 2015)

(b) intermediate payment 20% ( December 30, 2015)

(c)a month of partial payment, within three days from the date of receipt of the object, and 100% in cash;

7. Compensation for delay: 1/1,000 of the daily contract amount.

C. On December 2, 2015, the Plaintiff paid Defendant Company KRW 5,00,00,000 for the construction cost of the instant contract, and KRW 33,000,000 for the same month, and KRW 55,000,000 for the same month, and KRW 22,000,000 for the same month, and KRW 165,000 for the total amount.

Around January 4, 2016, Defendant Company suspended and resumed the instant construction work. Around April 8, 2016, Defendant Company again suspended the instant construction work after performing some lighting works.

After requesting the Defendant Company to resume construction several times, the Plaintiff notified the Defendant Company of the termination of the instant contract on April 27, 2016.

E. On May 26, 2016, the Plaintiff entered into a contract for the construction work with Samsan Co., Ltd. (the contractual amount of KRW 242,00,000,000, June 8, 2016, and July 22, 2016).

arrow