Text
1. Defendant B, D Co., Ltd., and F Co., Ltd., together with the Plaintiff KRW 646,460,406.
Reasons
1. Determination as to the claim against Defendant B, D, and F
(a) Indication of claims: To be as shown in the reasons for the claims;
(b) 1) Defendant B and D: Article 208(3)2 of the Civil Procedure Act [the case to which Article 150(3) of the Private Procedure Act applies] of the Defendant F: Article 208(3)3 of the Civil Procedure Act (the case to which the Defendant was notified of the date by public notice and did not appear on the date of pleading)
2. Determination as to claims against Defendant A and C
A. Fact 1) The Plaintiff, G institution, and H institution (hereinafter “H institution”)
) The K Development Project in Naju-si, JJ-si, hereinafter referred to as the “instant Project”).
(1) As the implementer of the instant project, Defendant A, etc. and the instant project creation work (hereinafter referred to as the “instant project”).
The contract was concluded with respect to the instant project. The area of the instant project is 7,34,00 square meters; the area ordered by the Plaintiff is 3,122,00 square meters (42.6% of the total area); the area ordered by G institution is 2,461,00 square meters (33.5% of the total area) and the area ordered by H institution is 1,751,000 square meters (23.9% of the total area) for each implementer is as shown in attached Form 1. The part for the instant project development project was 20.3,000 square meters for each project site for 20.3,000 square meters for 20.3,000 square meters for each project site for 20.3,000 square meters for each of the instant project site for 20.3,000 square meters for each of the instant project around October 15, 2012 and around 20, 2013-H on March 15, 2019.
At the beginning of the supply, water was temporarily supplied to some areas through J-Myeon water supply areas due to the development of water demand.
(hereinafter referred to as "temporary water supply method"). It is as shown in the attached Form 2.
The plaintiff, G institution, and H institution are temporary supply pipes for the implementation sections of the G institution in J-Myeon.