Text
Defendant
A Imprisonment for six months, and Defendant B shall be punished by a fine of 5,000,000 won.
However, the defendant A.
Reasons
Punishment of the crime
Defendant
A is the representative director of Defendant B, and Defendant B is a corporation established for the purpose of indoor construction business.
On July 21, 2014, the Korea Land and Housing Corporation awarded a contract for the installation of 12 elementary schools, including the 9 elementary schools, which were newly constructed in the C District, at the Daeung S S Complex, to the 12 elementary schools, middle and high schools, and the Dae S Complex Co., Ltd. subcontracted the above installation work to the Defendant B Co., Ltd. on or around August 2014.
A sewage-grade person shall not further subcontract any construction work he/she has subcontracted to any third person.
1. On October 1, 2014, Defendant A subcontracted all of the construction works on the 5 elementary and 3 middle schools in the above construction work at the office of B Co., Ltd. located in Sincheon-si, Sincheon-si, and subcontracted the subcontracted construction work again at KRW 115,324,00, approximately 95% of the subcontracted construction cost, and around that time, Defendant A re-subcontracted the subcontracted construction work by having E perform the said construction work at the same time and at the same place as indicated in the list of crimes in the attached Table.
2. Defendant B Co., Ltd. subcontracted the subcontracted construction work to six companies, the representative of Defendant A, in the above date, time, and place.
Summary of Evidence
1. Defendant A’s legal statement
1. A protocol concerning suspect interrogation of the defendant A by the prosecution;
1. A written statement;
1. Application of Acts and subordinate statutes to a certified copy of a written request for administrative measures by an enterprise that violates the Framework Act on the Construction Industry, a copy of the request for disposition of audit results, a copy of the notice of disposition of audit results by the Board of Audit and Inspection, a copy of the construction work execution contract (A), a construction work execution contract (G), a construction work execution contract (H), a construction work execution contract (I), a certified copy of the corporate registry
1. Crimes.