(영문) 서울중앙지방법원 2016.12.08 2015가합575698
용역비
Text

1. The Defendant’s KRW 1,222,247,200 as well as 6% per annum from January 12, 2013 to March 31, 2016 to the Plaintiff.

Reasons

1. Basic facts

A. On December 24, 2009, the Defendant was selected as a priority bidder for the Manmanium development project, which was promoted in the area of a housing site development project, which was promoted in the area of a one-time zone at the Dong-dong. 2) Accordingly, the Defendant entered into a sales contract with the Korea Land and Housing Corporation on the 2nd June 29, 2010 for the land for the construction of an apartment-type factory, support facilities, neighborhood living facilities, etc. (hereinafter “instant building”).

(hereinafter referred to as “the instant land sales contract”). B.

(1) On March 10, 2010, the Defendant entered into a contract for construction project management services between the Defendant and the Plaintiff, setting the contract amount as KRW 3,400,000 (excluding value-added tax) with the Plaintiff and entered into the contract for construction project management services with the following terms (hereinafter “instant management services contract”).

(c) Contract for construction project management services;

1. Name of service: CM management services for the construction of the Annivers design of the Anniversium;

2. Service amount: 3,400,000,000 won (excluding VAT separate, incentives separately).

5. Service period: The scope of services to be provided by the design phase 6 months from March 10, 2010 to November 9, 2012 (month 32 months), construction phase 24 months, and phase 2 months from the completion of construction, and Article 3 (Scope of Services) (1) (Plaintiffs) (the scope of Services) (1) shall be the basic services and the additional services or special services requested by A (Defendants) in connection with the main services, and the basic services shall be as follows:

Provided, That mutual consultation shall be held on additional services for additional duties or special duties.

1. Design and supervision: Review of designs and specifications corresponding to the Construction Technology Management Act and the relevant regulations - Design schedule management - Design and supervision such as review and confirmation of shop drawings and specifications - Design VE analysis - Quality reduction and quality improvement - LCC analysis.