(영문) 춘천지방법원 원주지원 2021.01.15 2020가단56836
공사대금
Text

The defendant shall calculate 30,700,000 won to the plaintiff and 12% per annum from September 10, 2020 to the day of full payment.

Reasons

Since there is no dispute between the parties that the Plaintiff did not receive KRW 30,700,000 out of the construction price after having constructed a door door to D elementary school on March 31, 2020 for the Defendant, the Defendant is obligated to pay to the Plaintiff delayed damages calculated at the rate of 12% per annum under the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings, etc. from September 10, 2020 following the delivery of the complaint of this case sought by the Plaintiff to the day of full payment.

The plaintiff's request is accepted.