(영문) 전주지방법원정읍지원 2015.08.25 2015가단234
물품대금
Text

1. The Defendant shall pay to the Plaintiff KRW 25,00,000 as well as 20% per annum from January 24, 2015 to the day of full payment.

Reasons

1. Facts of recognition;

A. The Plaintiff supplied the Defendant with fishery products from January 10, 2013 to May 26, 2014.

B. Around September 2014, the Defendant agreed to settle the amount of fishery products to be paid by the Defendant between the Plaintiff and the Plaintiff as KRW 40 million and pay it to the Plaintiff.

C. Around December 5, 2014, the Defendant repaid KRW 15 million out of the agreed amount debt of KRW 40 million.

[Ground of recognition] Facts without dispute, Gap 1, 2 (if there are virtual numbers, including each number), the purport of the whole pleadings

2. According to the above facts of recognition, the Defendant is obligated to pay to the Plaintiff the remainder of the agreed amount of KRW 25 million and the damages for delay calculated at the rate of 20% per annum from January 24, 2015 to the day of full payment, which is the day following the delivery date of a copy of the complaint of this case.

3. In conclusion, the plaintiff's claim of this case is justified and it is so decided as per Disposition.