Text
1. The Defendant: KRW 22,968,823 to the Plaintiff and KRW 5% per annum from May 2, 2014 to April 14, 2015.
Reasons
In light of the facts in the evidence Nos. 1 through 4, the Plaintiff entered into a lease agreement with the Defendant on August 24, 2012 with respect to the second floor of the 1st floor of the 3rd floor of the 1st floor of the 3rd floor of the 2012 building owned by the Defendant, and paid the Defendant the lease deposit amount of KRW 48 million, and the said real estate was awarded to E on April 2, 2014 in a voluntary auction procedure commenced under this court D, and the Plaintiff delivered the said real estate at that time, and on May 1, 2014, received dividends of KRW 25,031,177 out of the above lease deposit amount of KRW 48 million from the above auction procedure.
In light of the above facts, the Defendant is obligated to pay to the Plaintiff damages for delay at each rate of 22,968,823 won and 20% per annum as stipulated by the Civil Act from May 2, 2014 to April 14, 2015, which is the date of the ruling of this case where it is deemed reasonable for the Defendant to dispute about the existence and scope of the obligation to perform as to the Plaintiff from May 2, 2014 to the date of full payment.
Therefore, the plaintiff's claim of this case is accepted within the scope of the above recognition, and the remaining claim is dismissed as it is without merit.