(영문) 전주지방법원 2015.09.22 2015가단870
대여금 등
Text

1. The Defendants’ joint and several liability amounting to KRW 20,000,000 to the Plaintiff, and Defendant A from February 5, 2015 to Defendant B, and Defendant B from February 2015 to the Plaintiff.

Reasons

On August 11, 2005, the Plaintiff asserted that the Defendants lent KRW 25,00,000 to the Defendants on the due date set on September 25, 2005. Since the Defendants do not dispute this, the Defendants are jointly and severally liable to pay to the Plaintiff damages for delay at the rate of 20% per annum as stipulated in the Act on Special Cases concerning the Promotion, etc. of Legal Proceedings from March 1, 2015 to the date of full payment, as requested by the Plaintiff, on the following day after the copy of the instant complaint was served on the Plaintiff as requested by the Plaintiff.

Therefore, the plaintiff's respective claims against the defendants of this case are reasonable, and all of them are accepted, and it is so decided as per Disposition.

arrow