logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울남부지방법원 2016.02.05 2015가단51528
공사대금
Text

1. The Defendant (Counterclaim Plaintiff) paid KRW 12,323,520 to the Plaintiff (Counterclaim Defendant) and the amount from April 7, 2015 to February 5, 2016.

Reasons

1.The facts of recognition are examined together with the principal claim and counterclaim.

The defendant 1) The defendant TW Industry Co., Ltd. (hereinafter referred to as the "TM industry") shall be the third party MM industry.

2) From the perspective of the foregoing, the construction of steel frame and trgs (hereinafter referred to as the “instant Defendant Corporation”) among the tamper river and library interior works subcontracted by the Ccamper river and library tegratian Corporation (hereinafter referred to as the “Defendant Corporation”).

(2) The special description of the said re-subcontracted construction contract is indicated in the following: (a) the cost of construction was KRW 155,463,000 (including value added tax); (b) from January 10, 2013 to January 30, 2013; and (c) the compensation rate for delay was determined at KRW 3/100; and (b) the special description of the said re-subcontracted construction contract is indicated in the design drawings, specifications, (c) no omission is made when all construction works related to the installation of a single heat are applied: (d) the outer wall is not turfed; (e) the total cost of transport and equipment; (e) the installation of a H beam; and (e) the design drawings, specifications, (e) the steel scraper; and (e) the H beam beam drawings.

B. 1) On January 18, 2013, the Defendant: (a) installed the sn beamline among the instant Defendant’s construction works re-subcontracted by the Plaintiff and the Defendant (hereinafter “instant construction works”); (b) the instant construction works

(2) The main contents of the instant construction contract are as follows.

The construction period: The total amount on January 18, 2013 to February 15, 2013: 24,00,000 won: 80 won (29,410km) - Advance payment for the terms and conditions of settlement of the construction volume: (1) 20% of the contract amount; (2) 20% of the contract amount as of February 8, 2013: Payment for completed portion of 20% of the contract amount as of February 8, 2013: The above total amount is the amount equivalent to the direct construction cost for both expenses and labor expenses (5%) except for public expenses (5%) and the estimated terms and conditions, and the separate column for “other than additional tax and estimated construction work” is stated in the separate column for construction work. (c) The Plaintiff completed the instant construction work on February 18, 2013.

arrow