(영문) 광주지방법원 2018.02.20 2017가단500971
손해배상(기)
Text

1. The Defendant’s KRW 62,002,00 as well as 5% per annum from August 8, 2016 to January 19, 2017 to the Plaintiff.

Reasons

1. Facts of recognition;

A. The Plaintiff is a lessee who runs the sales business of an imported household with the trade name of “C” and leases 132,232 square meters (hereinafter “instant warehouse”) out of the first floor of Seo-gu, Seo-gu, Gwangju for storage of goods, etc., and the Defendant is a lessor.

B. On August 7, 2016, water supply managers installed in B apartments under the Defendant’s management, caused water to flow out to the instant warehouse, and the floor of the instant warehouse was flooded, and the Plaintiff discarded it because it was impossible for the Plaintiff to flow out part of the imported households and small products stored in the instant warehouse.

(hereinafter “instant accident”).

C. On August 11, 2016, the Plaintiff, the representative of the Defendant, prepared a written confirmation (hereinafter “instant confirmation”) stating that the amount of inundation damage caused by the instant accident is KRW 62,002,00,000, along with the investigation documents and field pictures of the amount of household flood damage caused by the instant accident, with the following:

CDDD / [Grounds for recognition] without dispute, entry and shape of Gap evidence 1 through 3, and 7, and the purport of the whole pleadings

2. According to the facts established prior to the determination of the cause of the claim, the fact that the plaintiff and the defendant confirmed that the amount of flood damage suffered by the plaintiff caused by the accident in this case is KRW 62,002,00 (this is not accepted the defendant's assertion that the amount of damage cannot be recognized due to the lack of objective and scientific appraisal). Thus, the defendant shall pay to the plaintiff 62,002,00 won for damages caused by the accident in this case and damages for delay calculated at the rate of 5% per annum under the Civil Act from August 8, 2016 to January 19, 2017, the delivery date of a copy of the complaint, and 15% per annum under the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings from the next day to the day of complete payment, barring special

As to this, the defendant is 10:00 after the accident of this case occurred.