1. The Defendant’s KRW 24,200,000 as well as 20% per annum from June 16, 2015 to September 30, 2015 to the Plaintiff.
Reasons
1. The following facts may be found either in dispute between the parties or in full view of the purport of the entire pleadings in each entry in Gap evidence Nos. 1, 3, and 4 and 5:
The plaintiff in the status of the party is a corporation that runs the business of processing and construction of stone and stone in his/her main office in his/her office in his/her office in his/her office in his/her office in his/her office in his/her office in his/her office and the defendant is a corporation that runs the business of creating metal structures, etc.
B. The Plaintiff and the Defendant entered into a tin construction contract between the Plaintiff and the Defendant 1) The Defendant, as the introduction of A, shall construct a multi-family house B on the ground from the Nam River Co., Ltd. (hereinafter “instant construction”).
(2) On February 21, 2014, the Plaintiff received a sub-subcontract of the instant construction work from the Defendant upon introduction of A on February 21, 2014. The main contents of the supply (construction) contract made between the Plaintiff and the Defendant at the time are as follows.
Article 2 (Supply/Construction Method) “B” shall ensure that the following goods are supplied to a place designated by “A” (Defendant).
1. A list of supply: Construction of stone materials;
2. Delivery place: The site of new C construction works located in B in the Si of Pakistan in Gyeonggi-do.
3. Delivery Method: “B” shall be manufactured after the survey of the site room in accordance with the standards required by “A” and supplied to the site.
4. Delivery period: In principle, the whole quantity of materials brought into Korea shall be stored and constructed from February 21, 2014 to March 15, 2014;
Article 3 (Value of Supply): Value-added Tax (Won 30,000,000): Amount of money in lump sum (Won 3,000,000): Amount of money in lump sum (Won 3,000,000): Amount of money in lump sum (Won 33,000,000): Amount of money in KRW 33,00,000 (Won 33,00,000
1. The balance of cash payment of 30% of the construction amount on February 28, 2014 shall be made in cash within 15 days after the completion of the work, for cash payments of 30% of the construction amount on March 10, 2014;
2. The cost of the delivery (construction) shall be claimed with a written claim for the issuance issued by the agent of “B” or “B”, and the time of termination of the delivery (construction).