logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울중앙지방법원 2016.01.20 2015가단5218481
전세금 반환 등 청구의소
Text

1. The Defendant: (a) KRW 100,000,000 for the Plaintiff and 5% per annum from December 26, 2014 to July 13, 2015.

Reasons

1. On December 23, 2011, the Plaintiff concluded a contract with the Defendant to lease subparagraph 606 of Article 606 of the Seongdong-gu Seoul Building Act, with the period from December 30, 201 to December 29, 2013, and paid KRW 10 million on December 23, 201, and KRW 90 million on December 30, 201, respectively. The said lease contract was terminated on August 25, 2014, and the said contract was terminated on November 25, 2014, and the said building was delivered on December 15, 2014, the Defendant deemed to have led to confession pursuant to Article 150 of the Civil Procedure Act.

2. Therefore, the Defendant is obligated to pay to the Plaintiff the amount of KRW 100 million and delay damages at each rate of KRW 5% per annum under the Civil Act from December 16, 2014 to July 13, 2015, on which a duplicate of the complaint of this case was served on the Defendant from July 13, 2015, and the interest rate prescribed under the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings from the following day to the date of full payment, or within the scope thereof, 15% per annum

3. If so, the plaintiff's claim of this case is justified and it is so decided as per Disposition.

arrow