(영문) 서울서부지방법원 2019.02.27 2018가단231645
양수금
Text

1. The defendant shall pay to the plaintiff KRW 95,838,288 and KRW 65,162,151 among them, from June 22, 2018 to the day of full payment.

Reasons

1. The indication of claim: the Defendant purchased C Truck (Ba Number D) and entered into a contract with E Co., Ltd. (hereinafter “E”) on the interest rate of KRW 86 million per annum, 10.9% per annum, 48-month equal repayment of principal and interest, and 25% per annum of overdue interest rate.

Since then, the above contract was terminated with the defendant's repayment of principal and interest, and E transferred the above loan claim to the plaintiff on June 28, 2017, and the same year.

7. 28. The Defendant notified the Defendant of the assignment of claims.

Therefore, the Defendant, a transferee, is obligated to pay to the Plaintiff the amount of KRW 65,162,151, overdue interest of KRW 30,676,137,28 as of June 21, 2018, plus KRW 95,838,288, and delay damages calculated at the rate of 25% per annum from June 22, 2018 to the date of full payment.

2. Judgment by service (Article 208 (3) 3 of the Civil Procedure Act).